Uzbekistan Suspends Irrigation Projects With China as Contractors Ask for Double the Price

Water Management Minister Shavkat Khamraev explained in parliament why not a single soum has been spent on the $130 million projects

Tempo:

AK
Anna Kuznetsova
· 2 min read
USD/UZS, last 30 days · NoorSada · Yahoo Finance

Irrigation projects in four regions of Uzbekistan financed by the Chinese Eximbank to the tune of $130 million have still not begun: contractors requested prices more than double the estimates. Water Management Minister Shavkat Khamraev named the reason on 11 November at "Government Hour" in the Legislative Chamber of the Oliy Majlis.

The question was raised by Imomnazar Tursunov, a deputy from the People's Democratic Party: work has not started on a number of investment projects planned for 2026. The discussion concerned the reconstruction of irrigation infrastructure in the Surkhandarya, Kashkadarya, Bukhara and Namangan regions. "The table presented shows that not a single soum has been spent on these projects," the deputy said.

Khamraev said the ministry had expected to bring in China's CITIC and CAMC: the contractors would start work with their own funds, and the costs would then be reimbursed through Chinese concessional loans. According to him, the companies submitted documents proposing to carry out the work not 10 or 20% more expensively, but more than twice the estimated cost.

Negotiations with them lasted more than a year and produced no result. After that the government turned to the Chinese side in order to organize financing through Eximbank in accordance with the established procedure: the bank's review of the project, including expert assessment, takes about six months, and roughly another year went on selecting contractors. Three companies took part in the tender, CITIC was named the winner, but "the winning company's price also turned out to be 20% higher." The ministry tried to negotiate a 20% reduction in cost, but the talks produced no result.

The ministry is now discussing terms with another large Chinese company, Sinohydro; the latest round of talks with its representatives took place on the morning of 11 November, before the parliamentary session. The minister said he does not intend to agree to inflated prices in order to speed up the work, since those funds would have to be repaid from the budget. "Therefore the matter is currently suspended," he said.

According to Khamraev, this is a large programme whose implementation will take at least two years. The project documentation has been developed and has passed expert review; the canal concreting work is expected to be carried out in 2027-2028.

President Shavkat Mirziyoyev signed the resolution (PP-409) on implementation of the projects earlier. The document provided for two projects with a preliminary total cost of $220 million. The customer was designated as the Center for the Implementation of Foreign Investment Projects in Water Management under the Ministry of Water Management, and the source of financing as concessional loans from the Export-Import Bank of China. As an exception, CITIC Construction Co. Ltd was designated general contractor for the Bukhara, Namangan and Surkhandarya regions, and for the Kashkadarya region, CITIC Construction Co. Ltd and China CAMC Engineering Co., Ltd. For the Kashkadarya project, 120 billion soums were to be allocated in 2025.