Acwa and Uzbekistan to assess four wind farms for carbon credits

Memorandum signed at UN climate conference in Antalya; the assessment will begin with the 1.5 GW Kungrad wind farm in Karakalpakstan.

Tempo:

AK
Anna Kuznetsova
· 2 min read
Red crane lifts blade onto white turbine tower under partly cloudy sky · Symbolbild · Photo: HansLinde / Pixabay

Uzbekistan and Saudi energy company Acwa will assess whether four wind projects in the country can generate carbon credits for sale on the international market. A memorandum of understanding was signed at the 31st UN climate conference in Antalya (Turkey).

For Uzbekistan the document was signed by the presidential adviser on ecology and chairman of the National Committee on Ecology and Climate Change, Aziz Abdukhakimov, and for the company by its founder and chairman of the board of directors, Mohammad Abdullah Abunayyan.

The review will begin with the 1.5 GW Kungrad wind farm, which is under construction in Karakalpakstan. The assessment also covers the Bash, Dzhankeldy and Karatau projects. The parties will check whether they meet the requirements of the Paris Agreement and how to obtain approval and registration under international carbon mechanisms. Separately, the agreement provides for improving procedures for verifying emissions data, as well as monitoring and reporting.

The sale of credits could become an additional source of income for the projects themselves. Under Article 6.4 of the Paris Agreement, the UN-backed mechanism allows projects to receive tradable credits for verified emission reductions; credits are issued only after the project is approved.

The agreement also covers climate risks for wind farms and energy storage systems: the parties plan to exchange data on how extreme temperatures and dust or sand storms affect equipment, and to use climate data in early warning systems.

Construction of Kungrad officially started in September. The project includes a 300 MW storage facility; to connect to the power system, about 930 miles of high-voltage lines, three new substations and the modernization of two existing ones are planned. The presidential administration estimates the project cost at $2.6 billion, Acwa at $3.07 billion; the buyer of electricity under a 25-year agreement is National Electric Grid of Uzbekistan.

According to Acwa's estimate, Kungrad will have five times the capacity of the company's two operating wind farms in Karakalpakstan - Nukus-1 and Nukus-2 - which together have 300 MW of generation and 100 MW of storage. Once all of Acwa's projects in the region are completed, their combined capacity will be about 2.3 GW, with output of about 8.77 billion kWh per year, enough to supply electricity to roughly 2.4 million households. This will save about 2.1 billion cubic meters of natural gas and avoid almost 5 million tonnes of CO2 emissions per year.

At peak construction, Kungrad will create about 4,000 jobs, and about $750 million of supplies and works could be sourced within Uzbekistan. The ecology committee did not say when the assessment will be completed or how many credits the project could receive.