Tesla commits 3 billion euros to Grünheide expansion for Cybercab output
The US carmaker says the first tranche lifts its total investment in Berlin and Brandenburg to nearly ten billion dollars, with Cybercab output planned from 2029.
ℹ️ Lecture par le navigateur · voix studio IA bientôt

Tesla will invest around three billion euros in a first step to expand its Gigafactory Berlin-Brandenburg, the company said on Monday, aiming for capacity of up to one million vehicles at its only European production site.
Plant manager André Thierig said the expansion would create "the basis for the world's most technologically advanced Tesla factory." The announcement lifts Tesla's total investment in Berlin and Brandenburg to nearly ten billion dollars, after the company opened a new development centre in Köpenick days earlier.
The plan centres on a production building of up to 75 football pitches in area — more than double the size of the existing factory hall in Grünheide. Tesla intends to build up to one million Cybercab electric vehicles there: a two-door limousine without steering wheel or pedals, designed to drive fully autonomously.
The existing plant is rated at around 375,000 electric cars a year, a figure never reached since production began in spring 2022; just over 200,000 Model Y cars rolled off the line last year. Output has been raised in recent months towards 7,500 vehicles a week.
Tesla did not say how many jobs the expansion will create, stating only that "many new jobs" would follow. It is immediately recruiting several hundred staff for construction and production planning. Around 11,000 people worked at the plant recently, with Tesla seeking up to 2,000 more for the production ramp-up and a further 1,500 for battery cell manufacturing planned for 2027.
The permit application, based on the 2023 application for the overall expansion, will be filed before the end of the year. Construction of the hall is scheduled for the first half of 2027, with production in the new facilities due to start in 2029.
Tesla says the site can be supplied within its contractually secured volumes from the Wasserverband Strausberg-Erkner across all expansion stages, through recovery and reuse of process water. Steffen Schorcht, deputy federal chair of Grüne Liga, said the risk of pollutants entering groundwater remains, along with restriction of groundwater flow from nearly 40,000 piles up to 17 metres long for the new hall's foundation.
Since Elon Musk announced the plant in November 2019, Tesla has invested more than six billion euros at the site. Expansion plans had gone quiet as sales fell in 2024 and 2025; before March's works council election, Thierig warned that a strong IG Metall result could stall the build-out. The union fell well short of a majority, and has since filed a criminal complaint against Thierig for defamation.