Uzbekistan aims to reach 500,000 tonnes of copper per year by 2030
Mirziyoyev instructed the creation of a full cycle — from copper mining to the output of finished products — abandoning a reliance on exporting raw materials.
ℹ️ Lecture par le navigateur · voix studio IA bientôt

President of Uzbekistan Shavkat Mirziyoyev, at a meeting with representatives of the electrical engineering industry and investors, announced a goal — to bring annual copper production to 500,000 tonnes by 2030 and to expand processing inside the country.
According to data presented at the meeting, the output of the electrical engineering sector grew from 1.7 trillion soums in 2016 to 50 trillion soums in 2026. Investment in the sector reached $600 million, and exports amounted to $1.6 billion.
Mirziyoyev said that further development of the industry requires not only expanding capacity but also modernizing technology. He named the creation of a full industrial cycle — from copper processing to the output of finished products — as the main priority.
The president recalled that construction of copper concentrating plants in Almalyk began on his initiative 10 years ago, when the world price of copper stood at $5-6 thousand per tonne; now it has reached $14 thousand per tonne. Mirziyoyev stressed that the country must not limit itself to exporting copper as a raw material and is obliged to earn more income through deep processing and the output of competitive finished goods.
The third copper concentrating plant was commissioned this year. According to the president, its launch will make it possible to bring copper production to 300,000 tonnes, and the next goal is 500,000 tonnes by 2030. Mirziyoyev estimated Uzbekistan's copper reserves at 47 million tonnes and called them the foundation for the long-term development of the industry.
Work is under way on projects for the fourth, fifth and sixth concentrating plants. According to the head of state, projects worth a total of $450 billion are to be implemented with partners over 10 years. The existing resource base, he noted, makes it possible to plan the development of the industry 20 years ahead.
Mirziyoyev pointed to copper and critical minerals resources, qualified young specialists and experienced entrepreneurs, as well as to the need to attract new technologies and develop innovative solutions. He called energy one of the key conditions for industrial growth: the share of "green" energy is planned to be brought to 54% by 2030.
A decision on measures to support entrepreneurs in the electrical engineering industry was signed recently. The president invited participants at the meeting to put forward proposals on taking the sector to a new stage of development and called on the industry to take responsibility for processing raw materials inside the country.