Pakistan installs inner dome at Chashma-5, 1,200 megawatts to come online in 2030

According to Al Jazeera's satellite imagery analysis, the dome was on site on November 7; Pakistan announced on November 10 that it had been completed, and the unit will generate electricity in September 2030.

Швидкість:

ℹ️ Озвучка браузером · студійний голос ШІ незабаром

MY
Mehmet Yılmaz
· 2 min read
Two cooling towers releasing steam plumes into a warm sunset sky · Ілюстративне фото · Photo: distelAPPArath / Pixabay

Pakistan seated the inner dome of the fifth unit of the Chashma nuclear power plant on November 10; the unit is planned to start generating electricity in September 2030 with its 1,200-megawatt design capacity. According to an analysis of satellite imagery carried out by Al Jazeera's open-source unit, the large circular body next to the reactor building was visible in imagery taken on November 7 and had been on site since at least April.

The ceremony was held with the participation of Prime Minister Shehbaz Sharif, Chief of Army Staff Field Marshal Asim Munir and Chinese officials. According to a statement from Pakistan's Press Information Department, Sharif congratulated the engineers, technicians and workers of the two countries for completing this stage 'much earlier than planned' and described the project as a symbol of 'clean and emissions-free' electricity generation.

The satellite imagery also recorded the stages of construction: on June 14, 2023 the site appeared almost empty, and on November 18, 2023 a dark circle appeared in the middle of the levelled ground. The reactor's first concrete was poured on December 30, 2024; Pakistan's Nuclear Regulatory Authority had issued the construction licence four days before that. On October 19, 2025 the circular wall began to rise among the cranes, and in the January and April 2026 images the structure had turned into an open-topped concrete cylinder. On April 9, 2026 a copper-colored circular body appeared to the north of the building, close to the anchor.

Pakistan's Dawn newspaper wrote on September 17, 2026 that the dome had been installed early; in the same period, Pakistan Atomic Energy Commission Chairman Raja Ali Raza Anwar said the project had become ready to complete the dome ahead of the projected date.

Pakistan and China signed an agreement worth about 4.8 billion dollars in June 2023 for the construction of the unit. The reactor is based on the third-generation Hualong One design developed by the China National Nuclear Corporation (CNNC); active and passive safety systems, a double containment shell and a 60-year design life are envisaged.

Four Chinese units that entered service between 2000 and 2017 are operating at Chashma, and two Hualong One units that came into service in 2021 and 2022 are operating at Karachi. Chashma-5 will thus be the seventh reactor China has built in Pakistan and the country's third Hualong One reactor. According to official figures, the total installed capacity of Pakistan's operating nuclear reactors is about 3,530 megawatts; the new unit will add 1,200 megawatts when it comes online.

At the ceremony, the commission chairman said nuclear power meets about 16.6 percent of the country's electricity, that this ratio rises to 26 percent in winter, and that its share of installed capacity remains at 8.6 percent.

The installation of the inner dome represents progress toward completing the containment system, but it does not mean that all construction work is finished or that the plant is ready for operation. Next comes the assembly of the outer dome. In China's similar Lufeng-5 project, the inner dome was installed in April 2024 and the steel structure of the outer dome in October 2025.