Uzbekistan Suspends Irrigation Projects with Chinese Companies Over Prices

Shavkat Khamraev: CITIC and CAMC requested more than twice the expected cost; not a single sum has been spent on the projects

Speed:

AK
Anna Kuznetsova
· 2 min read
USD/UZS, last 30 days · NoorSada · Yahoo Finance

Uzbekistan's Minister of Water Management Shavkat Khamraev said on November 11 in the Legislative Chamber of the Oliy Majlis that irrigation infrastructure reconstruction projects involving Chinese companies have been delayed due to disagreements over construction costs.

A deputy from Uzbekistan's People's Democratic Party, Imomnazar Tursunov, reported that several investment projects planned for 2026 have not been started at all. The discussion concerned the reconstruction of irrigation networks in Surkhandarya, Kashkadarya, Bukhara and Namangan regions. A project worth US$130 million was to be financed with the participation of the Export-Import Bank of China. "According to the table presented, not a single sum has been spent on these projects," the deputy said.

Khamraev explained that the ministry had initially planned to engage CITIC and CAMC: the companies were to start work at their own expense, with subsequent reimbursement of costs from concessional Chinese loans. However, they submitted price proposals significantly exceeding the ministry's expectations. According to the minister, the companies proposed carrying out the work "more than twice the expected cost," rather than 10% or 20% more expensive.

According to him, the ministry spent more than a year trying to agree on acceptable terms, but the negotiations failed. The government then turned to the Chinese side to organize financing through the Export-Import Bank of China. The bank has been reviewing the project for about six months, including an assessment, after which the contractor is selected from among several companies — these procedures took about another year. The winner proposed a price 20% above the initial estimate.

A tender was then held with the participation of three companies. CITIC won, but its price also turned out to be 20% above the planned one. It was not possible to persuade the company to lower the price. The ministry began negotiations with another large Chinese company — Sinohydro; a meeting with its representatives took place on the morning of November 11, before the parliamentary session.

Khamraev explained that if the high price were accepted for the sake of speed of work, "the money would ultimately have to be repaid from the state budget," so the issue has been postponed for now.

According to him, the program will take at least two years. The project documentation has already been prepared and has passed the necessary expert review. Concreting of the canals is planned for 2027–2028. The minister said the agency intends to carry out the work with quality and within the allocated budget.

On November 29, 2024, President Shavkat Mirziyoyev signed resolution PP-409 on the reconstruction of irrigation infrastructure in Bukhara, Namangan, Surkhandarya and Kashkadarya regions with the participation of the Export-Import Bank of China. The document provided for two projects with a preliminary combined cost of US$220 million: US$160 million for irrigation infrastructure in Bukhara, Namangan and Surkhandarya regions, and US$60 million for Kashkadarya region. The customer was designated as the Center for the Implementation of Projects with Foreign Investments in Water Management under the Ministry of Water Resources. CITIC Construction Co. Ltd was appointed general contractor for the three regions, and CITIC Construction and China CAMC Engineering Co., Ltd for Kashkadarya. For the Kashkadarya project, 120 billion sums were reserved from the local budget for 2025 for a 15-percent advance payment.