79 GW Under Development... Saudi Arabia Opens Qualification for a 3.2 GW Renewable Round

Energy Minister Prince Abdulaziz bin Salman announces the figure at COP31 in Antalya, and the Saudi Power Procurement Company opens qualification for an eighth round in Makkah, Riyadh and Asir.

Speed:

ℹ️ Browser-based reading · AI studio voice coming soon

YA
Yusuf Al-Saadi
· 2 min read
Wind turbines in misty field under pink and blue sunrise · Representative image · Photo: Tama66 / Pixabay

Minister of Energy and Minister of Industry and Mineral Resources Prince Abdulaziz bin Salman announced that the total capacity of renewable energy projects under development in Saudi Arabia has reached about 79 GW, as part of a target to raise the share of renewable energy sources to 50 percent of the electricity mix by 2030, which supports the diversification of electricity generation sources and reduces reliance on liquid fuel.

The minister's announcement came during his participation in the 31st Conference of the Parties to the United Nations Framework Convention on Climate Change "COP31" in Antalya, and coincided with the Saudi Power Procurement Company's announcement of opening the qualification process for developers to take part in the eighth round of the National Renewable Energy Program, which includes three solar and wind projects with a total capacity of 3.2 GW.

At the forefront of the round is the "Al-Muzayri'ah" wind power project with a capacity of 1.3 GW in the Makkah region. The tender also includes the "Tumayr" solar project with a capacity of 900 MW in the Riyadh region. As for the "Sharq Al-Amwah" project, its capacity is one gigawatt in the Asir region. The offered capacities are thus distributed between 1.9 GW of solar energy and 1.3 GW of wind energy.

Opening the qualification process represents a preliminary stage in the competition procedures, as the Saudi Power Procurement Company prepares the preliminary studies and puts the projects out to tender, before completing the competition procedures, selecting the developers and signing the power purchase agreements. The announcement therefore does not mean that construction of the plants has begun or that their contracts have been awarded.

The National Renewable Energy Program, which is supervised by the Ministry of Energy, aims to reach capacities ranging between 100 and 130 GW by 2030, according to the renewable energy projects tracker issued by the King Abdullah Petroleum Studies and Research Center "KAPSARC".

The tracker records about 70 GW of capacity distributed across 58 projects, according to September 2024 data, of which 17 projects are operating and 24 are under development. As for the projects put out to competition, their number is 17. This figure is lower than the minister's figure of 79 GW, a difference that highlights the importance of distinguishing between capacity under development and capacity that has entered the construction or operation phase when measuring progress toward the targets.

The expansions extend to battery-based electricity storage systems. According to the Kingdom's second Nationally Determined Contribution document submitted to the United Nations Framework Convention on Climate Change, the total capacity of energy storage projects put forward by Saudi Arabia is about 30 GWh, of which 8 GWh has entered the operation and grid-connection phase, while the remaining capacity of 22 GWh is distributed across projects that are still in various stages of development.

The projects are distributed among local developers and companies affiliated with the Public Investment Fund, including "ACWA" and "Badeel", alongside the Saudi Aramco Power Company "SAPCO". On July 14, 2024, the Saudi Power Procurement Company signed power purchase agreements for seven new projects with a total capacity of 15 GW and initial investments estimated at about $8.3 billion, with the participation of a consortium led by "ACWA Power" and including "Badeel" and "SAPCO". In November 2024, "ACWA" announced the completion of financial close for the seven projects, with an investment value of $8.2 billion (SAR 31 billion).

The seven projects are distributed across five photovoltaic solar plants with a total capacity of 12 GW, and two wind plants with a capacity of 3 GW. The solar plants include "Bisha", "Al-Humayj", "Khulais", "Afif 1" and "Afif 2", while the wind projects include the "Starah" and "Shaqra" plants, which are scheduled to enter service successively during the second half of 2027 and the first half of 2028. The Public Investment Fund aims to develop 70 percent of the Kingdom's targeted renewable energy capacity by 2030.